Texas Legislature · Economy & Taxes
Bipartisan bills would end a data center tax break on track to cost Texas $1.75 billion a year
The sales tax break cost an estimated $1.3 billion in fiscal 2026, and the Comptroller projects $1.75 billion by 2030. A Senate repeal bill has 23 authors from both parties.
Disclosure: The Landmark's owner is a partner in a public affairs firm that works on data center projects.

Texas gave up an estimated $1.3 billion in state sales tax in fiscal 2026 through a tax break for large data centers. Senators from both parties have filed a bill to end it before the Legislature meets Jan. 12.
The estimate comes from the Comptroller's January 2025 report on tax exemptions, which projects the cost rising to $1.753 billion by 2030.
The break dates to 2013. It exempts electricity and equipment for data centers of at least 100,000 square feet that create at least 20 qualifying jobs and invest $200 million over five years. A second tier, added in 2015, covers projects of at least 250,000 square feet with 40 jobs and $500 million, according to the report.
The bills
Senate Bill 293, by Republican Sen. Joan Huffman, would repeal both exemptions. Texas Legislature Online lists 22 other senators as authors, including Democrats Carol Alvarado, Juan "Chuy" Hinojosa, Royce West and Judith Zaffirini. Those party labels are from the Legislative Reference Library's 90th Legislature roster. TLO lists four similar House bills, including HB 681 by Rep. Cody Vasut and HB 167 by Rep. Trey Martinez Fischer.
SB 338, by Sen. Charles Perry and 15 co-authors, is narrower. It would cap a city's property tax abatement for a data center at half the value otherwise eligible. Data centers getting abatements or state school-tax limits would have to use water-efficient cooling and report water use each year to the Public Utility Commission. Cities could cancel a deal and recover lost taxes if a company broke its terms.
The grid
The Electric Reliability Council of Texas was weighing about 474 gigawatts of requests to connect to the grid in early August, about 90% of them data centers, according to Gov. Greg Abbott's Aug. 3 letter ordering an audit. That is "more than five times Texas' record peak electricity demand," the letter says.
ERCOT paused approvals to energize new data centers and crypto mines of 75 megawatts or more. It must file a verification report and a community impact review with the PUC by Dec. 10.
In September, ERCOT conditionally kept 204 projects totaling 66.4 gigawatts in line, put 158 more in a group to be studied, and excluded 373 projects totaling 302.2 gigawatts. On Nov. 5, it told the PUC that common problems included developers who couldn't show site control or financial security.
What it brings in
A Baker Institute working paper estimates Texas data center investment at $66.2 billion in 2026, up from $3.4 billion in 2022. It estimates the taxable value of data center property in Texas at about $32.18 billion, out of $39.79 billion in market value.
Direct jobs are a smaller story. Federal wage records show 47,535 private jobs in Texas in March 2026 in the industry that includes data centers, data processing and web hosting, 447 fewer than a year earlier. The industry's average weekly wage was $3,825.
Construction is where the money shows up. The Comptroller said construction-sector sales tax collections in October were up 38% from a year earlier and "may reflect investment in large-scale projects, including data centers." The Dallas Fed's Nov. 25 Beige Book cited "continued reports of data center construction pushing up labor costs and pulling workers away from other industries."
What it means
A data center can be a good neighbor for a Texas county. It adds taxable property to the local roll and brings construction work. The questions are what the public gives up to get one and what the community gets back.
On the state's side, the price is rising fast: from about $1 billion to a projected $1.75 billion a year by 2030, for projects that must create as few as 20 jobs. The Texas Taxpayers and Research Association told senators in July that the break puts data centers on par with manufacturing, which has its own exemption. The difference is growth: the Comptroller projects the data center break's cost will rise about 73% from 2025 to 2030, compared with about 34% for the manufacturing exemption.
SB 293 would end the break outright. SB 338 would keep local deals but attach conditions: water-efficient cooling, annual water reports and money back if the company walks away. That approach asks the questions Abbott's Aug. 3 letter asked: does the project pay its way, bring its own power and water, and protect the people next door?
ERCOT's Dec. 10 reports will be the first public test of how many projects pass.