McKinney City Council · City Hall
McKinney’s gun range is nearly out of money after another contract increase
The architect’s contract has grown from $32,000 to $110,750, more than three times the 2022 agreement. After two more changes approved Nov. 17 without discussion, $5,184 remains in a $1,378,712 budget.

McKinney’s contract with the architect for a police gun range building has grown from $32,000 to $110,750. The City Council approved the latest increase on Nov. 17 as part of its consent agenda, the group of items passed in one vote without discussion.
The project is a new storage and workshop building of about 2,400 square feet, with restrooms, plus new pavement at the Police Department Gun Range.
The council approved a second change the same night: up to $75,000 more for the builder, Crossland Construction Company, Inc. After both, the project has $5,184 left in its $1,378,712 budget, according to the staff reports.
How the design contract grew
The city hired Conduit Architecture + Design, LLC of McKinney for the gun range in 2022, for $32,000. “Since that time, the project scope has evolved,” the staff report says. The city then signed three more agreements with Conduit, bringing the contract to $98,250.
The new $12,500 agreement pushes the total to $110,750, past the $100,000 mark that requires council approval, the report says. The council authorized up to $15,000, including a $2,500 contingency.
- Original agreement: $32,000
- Three more agreements bring the total to $98,250The staff report doesn’t list their dates or amounts.
- Council approves $12,500 more, for a total of $110,750Up to $15,000 with contingency. Resolution 2026-11-215.
Source: City of McKinney, Staff report 26-1101; draft minutes, Nov. 17, 2026, staff report; minutes p. 6
The report says the new work covers “unforeseen field conditions requiring revisions to civil plans, structural pier design, and water and irrigation systems.”
The construction contract
On May 19, 2026, the council approved a guaranteed maximum price of $1,119,956 for Crossland to build the project, with completion expected in May 2027.
The city left an owner’s contingency out of that price “to maintain the project within its original approved budget,” the staff report says. Extra work so far has come out of Crossland’s own contingency. The $75,000 amendment refills that money and creates an owner’s contingency. The report doesn’t say how much of Crossland’s contingency has been used.
Source: City of McKinney, Staff reports 26-1101 and 26-1096, Source of Funds tables, Financial Summary
The same table lists “Project Contingency / Other Project Costs” as “TBD.”
The vote
The draft minutes show the council approved the consent agenda unanimously, on a motion by Council Member Patrick Cloutier, seconded by Mayor Pro Tem Rick Franklin. One item, 26-1099, was pulled for discussion. The Crossland amendment is Resolution 2026-11-210, and the Conduit agreement is Resolution 2026-11-215. The minutes are a draft until the council approves them.
Approve the consent agenda, except item 26-1099 (includes 26-1096 and 26-1101)
7–0Passed unanimously, per draft minutes
- Bill CoxMayorYes
- Rick FranklinMayor Pro TemYes
- Justin BellerYes
- Patrick CloutierYes
- Geré FeltusYes
- Michael JonesYes
- Ernest LynchYes
Source: City of McKinney, Draft minutes, McKinney City Council, Nov. 17, 2026, pp. 1, 3
The staff report says Conduit is one of five firms the city pre-qualified in 2025 for architectural work. Its 2022 hiring for this project came before that list existed. The reports don’t say how the 2022 contract was awarded.
What it means
The architect’s contract is now more than three times the 2022 agreement, and after the Nov. 17 votes the project has $5,184 left in a $1,378,712 budget. That is less than four-tenths of 1% of the budget. The staff reports list “Project Contingency / Other Project Costs” as “TBD.” They do not say where money would come from if the work runs past what is left.
The council approved both changes on the consent agenda, without discussion, unanimously, according to the draft minutes. The remaining cushion is thin. The records in hand stop there.