Collin County’s jail and courthouse bond is allocated. It isn’t built yet.

The county has assigned almost all of the $261.9 million to named projects, but spent and committed work still leaves $220.9 million unspent. Commissioners moved $179.7 million out of a contingency line on Nov. 9. The $50 million juvenile detention expansion hasn’t spent a dollar.

The Collin County Courthouse, a tan and brick building with a glass dome, in McKinney, Texas.
The Collin County Courthouse in McKinney, the building whose expansion and remodel are funded by Proposition A. Photo: Larry D. Moore, June 29, 2014. CC BY 4.0. Source.

Collin County has spent $15.0 million of the $261.9 million set aside for Proposition A, the jail and courthouse part of its 2023 bond program, according to a county project sheet for fiscal 2027.

Another $25.9 million is committed under contracts. That leaves $220.9 million not yet spent or committed.

On Nov. 9, in a special session, the Commissioners Court moved $179,683,252 out of the Proposition A contingency line and into named projects. The court order says the motion carried “by a majority of the court members in attendance.” It marks Commissioner Cheryl Williams as not present and gives no vote count.

Where the $179.7 million went

Before the move, $182,898,444 of the bond’s budget sat in one line, “Proposition A Discretionary.” That’s 70% of the $261.9 million. A county budget entry attached to the order shows where the money went.

Money moved out of the Proposition A contingency, Nov. 9, 2026
  • Courthouse expansion and remodel$88M
  • Juvenile detention expansion$50M
  • Jail kitchen move$23.4M
  • Courthouse parking garage$17.2M
  • Jail expansion and remodel$1.1M

Total$179.7M

Source: Collin County, Project Budget Adjustment Entry 386, p. 1

After the move, $3,215,192 remains in contingency, the amount the project sheet lists as authorized for that line.

Where the money stands

Proposition A, authorized amount by projectSpent and committed so far in each row
  • Courthouse expansion and remodelSpent $5,297,106 · committed $15,331,442$145M
  • Juvenile detention expansionSpent $0 · committed $0$50M
  • Jail kitchen moveSpent $837,549 · committed $728,217$25M
  • Courthouse parking garageSpent $909,771 · committed $1,229,158$19.9M
  • Jail expansion and remodelSpent $6,000,228 · committed $8,608,726$16.7M
  • Juvenile probation move (Plano)Spent $1,995,147 · committed $26,271$2.1M
  • Contingency$3.2M

Total$261.9M

Source: Collin County, 2023 Bond Election Project Summary – Proposition A, FY 2027, Fund 4032, p. 1

The biggest project is the courthouse expansion and remodel, at $145 million. It has spent $5.3 million, almost all of it on architecture. Construction spending so far is $66,605.

The juvenile detention expansion is set at $50 million. The project sheet shows no budget, no spending and no contracts for it before the Nov. 9 move.

The only project close to done is the move of the juvenile probation office in Plano. It has spent $1,995,147 of $2,070,000. Its construction line is over budget by $2,879.65.

The jail kitchen

The court’s Nov. 16 agenda included a $20,101,519 guaranteed maximum price from Sedalco, Inc. for the third phase of moving the jail kitchen. A memo from Director of Building Projects Sandeep Kathuria says “Funds are available in the 2023 Bond Funds.”

Sedalco is the county’s construction manager-at-risk for the kitchen project. The county’s purchasing memo says any increase to that price would come back to the court before the work is authorized. The kitchen move is set at $25 million. Before the price came in, the project had spent $837,549, all on architecture.

The cost of borrowing

The same Nov. 16 agenda asked the court to approve $1,763,566.85 in spending tied to the county’s 2026 bond sale under the 2023 bond election. The detail sheet lists it as costs of issuance and underwriter discounts. Of that, $295,603 is charged to the Proposition A fund.

What it means

The county has now put names on almost all of the $261.9 million. It has not spent it. After the Nov. 9 transfer, only $3.2 million remains in the contingency that once held 70% of the program. Spent and committed together still leave $220.9 million unspent. The $50 million juvenile detention expansion, funded in full that day, shows no spending and no contracts.

The courthouse project is the largest line, at $145 million, and has spent $5.3 million, almost all of it on architecture. Construction spending on that project is $66,605. The one job close to done is the Plano juvenile probation move.

What comes next is only partly in the record. The $20.1 million Sedalco price for the jail kitchen and the $1.8 million in 2026 bond-sale costs were on the Nov. 16 agenda. The court’s action on those items has not been posted, so this story does not treat them as approved. The bond is allocated. It is not, yet, built.

See a mistake? Request a correction. Highlighted figures link to the page of the public record they came from.